Lien rights arise under the Builders Lien Act, SBC 1997, c 45. There is no preliminary notice requirement in BC; a 'mechanics lien' preliminary notice is a US concept. A contractor, subcontractor, worker or material supplier who has not been paid preserves its lien by filing a claim of lien in the Land Title Office against the land improved. The deadlines are strict. A claim of lien must generally be filed within 45 days after a certificate of completion is issued for the contract or subcontract, or, if none is issued, after the head contract is completed, abandoned or terminated, or the improvement is completed or abandoned (s. 20). The lien is extinguished unless the claimant commences an action to enforce it and registers a certificate of pending litigation within one year after the claim of lien was filed (s. 33). An owner can shorten this by serving a notice requiring the claimant to start its action and register a certificate of pending litigation within 21 days, failing which the lien is extinguished (s. 33). Owners must keep a 10 percent holdback from payments under the contract, and the lien attaches to that holdback. An owner or contractor can clear title by paying money into court or posting security under s. 24, and the court can cancel a claim of lien that is frivolous or an abuse of process (s. 25(2)). Only the court, in an enforcement action, can order the land sold. Agreements that try to exclude the Act are void (s. 42(2)). Filing a lien carries risk. A person who files a claim of lien against an interest in land to which the lien does not attach is liable for the resulting costs and damages of the owner (s. 19), and knowingly filing a claim of lien containing a false statement, such as an inflated amount, is an offence with a minimum fine (s. 45).
For contractors and suppliers, a builders lien is often the most effective way to get paid, because it secures the debt against the land and pressures the owner and lenders. Missing the 45 day filing window or the one year enforcement deadline loses that security. For owners and developers, liens can freeze construction financing and sales, so managing holdbacks and clearing liens quickly by posting security is essential. Example: An electrical subcontractor on a Surrey industrial build is unpaid when the general contractor walks off the job. It files a claim of lien within 45 days of the contract's termination, and the owner posts security under s. 24 so its construction lender will keep funding.
Filing a 'preliminary notice' or waiting for one, when BC has no such requirement. Missing the 45 day deadline by counting from the wrong triggering event. Forgetting to start an action and register a certificate of pending litigation within one year. Inflating the lien amount, which can be an offence under s. 45 and invites an application to cancel the lien. Owners failing to retain the 10 percent holdback, which leaves them exposed to subcontractor liens.
How long do I have to file a builders lien in BC?
Generally 45 days after a certificate of completion is issued or, if none, after the contract or improvement is completed, abandoned or terminated. The lien must then be enforced by an action and a certificate of pending litigation within one year.
Does BC require a preliminary notice for a builders lien?
No. Preliminary notices are a US requirement. In BC, lien rights arise automatically under the Builders Lien Act and are preserved by filing a claim of lien in the Land Title Office within the statutory deadline.
How can an owner remove a builders lien from title in BC?
By paying the claimed amount into court or posting security under section 24 of the Builders Lien Act, which removes the lien from title. An owner can also apply to cancel a lien that is frivolous or an abuse of process.
Lien | Lien waiver (Builders Lien Act) | Construction contract | Clearing title | Land title
Filing or defending a builders lien? Talk to a Fulcrum construction lawyer.
General information about British Columbia and Canadian law, current to October 2026. It is not legal advice; get advice on your own situation.